In connecting a sales contract to a project, Add Project Activities to Contract Line Item functionality, one prerequisite is that
- Only activities that have not already been connected to a line item within that contract can be added
Is there a specific reason for this? Can’t it be done the same way that more than one activities can be connected to an item by giving each a weight?
TIA
Best answer by Tharindu Illangasinghe
View original