… and I am trying to find out why when:
- The demand comes from a work task (on a work order) which is project connected
- We run PMRP per activity (for all activities within the project)
- PMRP generates a shop order requisition for the top part (demand from work task)
- But no purchase requisitions for the components
- In MRP part information for the components, the gross requirement is 1 but net requirement 0 so it seems it “sees” the demand from the top part
- No MTRs generated, no stock
- Structure is buildable, components are not standard planned
- Structure phase in is way back in time and no phase out date
So what are we missing? Any ideas? We are running IFS Cloud 22R2.