Hi
We are using Apps 10 and MRP to schedule our shop order operations.
We have a contract that has a constant demand every month of 16 units, the product has a 15.5 day variable lead time to manufacture and we backward schedule.
When MRP schedules our operations backwards from the customer order line want date (end of each month), is plans to start manufacturing in the second week of each month.
is there a way we can get system to plan to build 4 unit per week every week to steady the flow of supply ?
regards
Jamie