We are using IFS 10 UPD9.
When the operators create a new MRB the status goes to Created.
However, on a least 3 cases the MRB went into status Planned. We can’t figure out what is making the status be Planned vs Created.
Planned doesn’t even seem to be a valid status (doesn’t show in the search options).
Can anyone shed some light on why MRBs sometimes create in status Created and sometimes Planned?