Question

APB urgent

  • 20 December 2021
  • 5 replies
  • 146 views

Hi, what is the effect of the utilization and % in group of the person ID in the Manufacturing Labor Class window on the available load of the Labor class in the advanced planning Board. 

 

Thanks.

 


This topic has been closed for comments

5 replies

Userlevel 4
Badge +9

Hi 

There is no effect. APB will not take that in to account. I quote here the tooltip.

Hope this helps

Saman

 

Hi 

There is no effect. APB will not take that in to account. I quote here the tooltip.

Hope this helps

Saman

 

thanks but what parameter is used on APB to modify the available load of the labor class

Userlevel 4
Badge +9

Hi Adam,

I really do not get this // what parameter is used on APB to modify the available//. Could you elaborate more with an example?

Thanks and regards

Saman

Hi Saman,

For example, if I want an ID Person to work half of the time on a Labor Class and the other half on another Labor Class. How to make her available load visible on APB ?

Thank's.

Hey @Saman K , can you answer my question? Thank’s