2 questions on the advanced planning board

 

  1. Does the APB consider Shop Order Priority Categories and prioritize accordingly?

 

  1. Can the APB use characteristic sequencing during automatic scheduling when loading shop orders and/or during scheduled batch loading, or is the only way to use sequencing a manual process within APB? 
icon

Best answer by Saman K 5 September 2022, 22:08

View original

1 reply

Userlevel 4
Badge +9

Hi,

  1. Yes ( as the priority category adjust the adjusted dates and it is adjusted dates that are the input to scheduling logic)
  2.  No Cant  ( our next Generation finite schedule solution will be able to do this)

Thanks and Regards