System is assigning HP tickets outside SLA

  • 24 January 2023
  • 3 replies
  • 42 views

Userlevel 3
Badge +8

Hi All,

We are facing issue as P3 task which is having 3 days SLA are getting assigned after 10 days, after breaching SLA. 

Can some one give me the solution.

 

Regards,

Shiyaz

icon

Best answer by Sajith Anushan 24 January 2023, 11:56

View original

3 replies

Userlevel 6
Badge +21

Hi Shiyaz,

Are you certain that SLA is restricted to 3 days? May be you might have multiple SLAs spanning across 10+ days. Otherwise, PSO will not allocate an activity outside SLA period.

Regards,

Sajith

Userlevel 3
Badge +8

Hi Sajith,

Thanks for your answer, Basically we have 3 types of SLA.

1st SLA, 2nd SLA & 3rd SLA.

But system should consider 1st SLA when it assign a fresh task, instead of considering the Last SLA date

How can we acheive it.

Regards,

Shiyaz

 

Userlevel 6
Badge +21

Hi Shiyaz,

Ensure that,

  1. 1st SLA is having Start/End proportions than other 2 SLAs.
  2. Activity has sufficient Base Value compared to low priority activities. 
  3. SLA curve is downward sloping.

Still it is possible that 1st SLA to miss but with a valid reason (like no skilled resources, other high priority activities are already allocated etc.).