PSO will broadcast the allocation details of all the visits of the split activity but, FSM will only capture the allocation details of one visit (the visit it captures is random - it may be the 1st, 2nd or 3rd visit) and display it in the task screen. But, only the last visit details are sent back to FSM & this is a incorrect representation for the Schedule.

 

For Example:  PSO Task is split into 3 days, Day1, Day2 & Day3, but the visit returned is for the Day3, the Scheduling for material planning will be done incorrectly considering the Day3. Whereas the Day1 is suppose to be considered for the Scheeduling.

Hey @CKOppBox 

Do you have a question?

Unfortenatly, this is the expected behaviour by design. 😓

FSM6 does not support split task functionaltiy.