Question

PM Setting start date is not matching with Planned date in maintenance Plan


Userlevel 1
Badge +4

I am wondering why sometimes the PM setting start date is not matching with planned date in maintenance plan.
I think something went wrong on the specific PM line because others PM line in same contract created correctly.


Any help would be greatly appreciated.

Thanks,
 

 

 


4 replies

Userlevel 6
Badge +12

Hi @rifasraja 

 

Please check the calendar ID you have connected on PM settings line. If the schedule connected to your calendar is having Saturday defined as a non working day, I assume that might be one reason, since your starting date, 5th Nov 2022 is a Saturday. Also please check the exceptions connected to your calendar as well (header of calendar you can find this) where you can define specific days and times when the normal working times are not applicable due to a holiday or scheduled work break. 

Userlevel 1
Badge +4

Hi @Dilini Arandara 

We got the problem now. I will inform the same to the end user.

 

Thank you for your valuable support.

Userlevel 6
Badge +12

Hi @rifasraja was it due to Saturdays being defined as a non working day? 

Userlevel 1
Badge +4

yes @Dilini Arandara as you correctly identified, the calendar ID which is connected to pm setting line is defined friday and saturday as a non working day.