Hello,
A customer of mine, is wanting to use object access as opposed to person groups for the project LU.
I have set the object access level as View for Projects, Subprojects and Activity.
I have been testing this access, and it seems that even though my user is not connected to the project and company- the user is still able to view the documents in the document revision screen.
I would have assumed that if the user did not have access to the company, and project, that they would then not be able to view any of the documents associated to the project object LU.
Do we have to use project access, with the object level access for this to work properly?
Unsure as to whether the object level access is there purely to define the maximum level of access that can be granted, instead of actually controlling which users have access to the object defined.