Question

Supplier Schedule Transfer

  • 6 June 2022
  • 1 reply
  • 89 views

Badge +2

Hello,

 

I have released as supplier schedule and am trying to generate a new schedule. When I run MRP again, a new schedule does not generate even when new demand requirements have been entered in the system. Do I have to transfer the schedule first before MRP can generate a new supplier schedule? I have selected the manual transfer option in the supplier schedule agreement part, but when I try to transfer the schedule I get an error message stating:  the the message transfer is not enabled for supplier. What setting do I have to enable to transfer the schedule?

 

Thanks,


1 reply

Badge +2

This question can be disregarded. I had a value entered in the Frequency field on the supplier schedule agreement part which is why MRP was not generating another schedule. 

Reply