We recently began using MRP and DDMRP to create purchase reqs for our planning method “G” and “H” parts. We are having an issue though, because when we allow MRP to create the purchase reqs for a work or shop order, the system does not reserve the material to the work order or shop order when it comes in.
Is there a way, or a background job that we can run that will auto reserve material to work orders and shop orders where MRP created the purchase req required for the work or shop order?
Thanks,
Sarah
Best answer by majose
View original