One example :
A calculated leadtime for a Purchase Part gives 92 days: Supplier Manufacturing Leadtime 42 days, External Transport Leadtime 10 days, Internal Transport Leadtime 40 Days Distribution Calendar 5 working days a week.
Purchase Proposals is created by a leadtime on 108 days.
Can someone explain the difference. From my perspective it seems that leadtime calculation is not using same calender as order proposal for Internal Transport Leadtime. (IFS version 10).
This result in wrong information on Inventory Part as well as Inventory Part Availability Planning.
Manual order also verifies leadtime as Order proposals.
From application help Internal Transport leadtime shall be using internal Distribution Calendar. But it does not.
Do anybody have faced this problem before and/or have a good explanation.