WADACO - Start Picking

  • 20 July 2023
  • 2 replies
  • 71 views

Userlevel 1
Badge +2

Hello everyone,

 

Does anyone know which subprocess WADACO - START PICKING takes first when actually starting the pick?

For example, I am creating a PickList (in which there is Handling Units and Parts) and the Customer wants to Report all the Parts frist and only then the Handling Units.

 

How can I do this in WADACO? Because sometimes it is starting with Handling Units and the other times it is starting with Parts….

 

Does anyone know how to solve this issue?

icon

Best answer by Mikko K. 24 July 2023, 13:55

View original

2 replies

Userlevel 4
Badge +6

Hi,

 

if the PICK_LIST_NO_LEVEL has List of Values as “Auto Pick” the system will choose either Part or Handling Unit depending on which happens to be first on the Pick List.

 

Edit “Auto Pick” to “On” and the user has a say in the matter.

 

Userlevel 1
Badge +2

Hi,

 

if the PICK_LIST_NO_LEVEL has List of Values as “Auto Pick” the system will choose either Part or Handling Unit depending on which happens to be first on the Pick List.

 

Edit “Auto Pick” to “On” and the user has a say in the matter.

 

Thanks ! This was exactly what I was looking for !