Solved

Chaining or Linking Two WaDaCo Processes

  • 5 January 2023
  • 4 replies
  • 148 views

Badge +2

How can we link two separate custom WaDaCo processes together? 

icon

Best answer by Dario Zani 9 January 2023, 09:51

View original

4 replies

Userlevel 7
Badge +22

Hi @Manohari 

you can link two wadaco processes via the marked fields. 

If the first process is completed the second one will start.

 

 

Badge +2

Hi @Link,

Thank you for the help!

I have two WADACO processes RESERVE_PACKAGES and PICK_PACKAGES as follows that needs to be linked together.

I have added values to the marked fields according to your previous reply and now it starts pick package WADACO process after it completes the reserve package WADACO process.

 



When it starts pick package WADACO process it did not get the order_no value automatically from the reserve package (first process) process. We need to enter it again in the pick package process.

Is there a way to get a specific data item values like order_no from first process to second process automatically? Do I need to change any configuration setup to achieve this?

Userlevel 7
Badge +22

Hi @Manohari 

that means you want to transfer the parameters from the first process to second process. 

I am not sure if it is possible. I never had that case. But I don’t think so. 

Userlevel 6
Badge +16

Check how the regular process ‘Report Picking of Customer Order Lines’, you can see how it get/sends the value from one process/session to another, the key fields are ‘Subsequent Data Item ID’ and ‘Use Subsequent Value’.

 

 

Reply