Question

Transport task Consolidation

  • 5 December 2023
  • 2 replies
  • 50 views

Badge +3

Hi,

In our current process, we reserve materials for our shop orders in the warehouse. Next step, we move those parts to the “pre-production” using transport tasks (warehouse task on WaDaCo). To do this, we go to the screen ‘inventory parts in stock reservations”, select everything for the same DOP and create the transport task.

 

As we have have big structures with many phantoms, the same part pops up several times in our transport tasks. We now have situations where the operator needs to execute 10x a line, for the same part at the same location.

I can’t figure out which setting to use to consolidate these lines. Can someone help?

 

This is the current setting on site level:

 

Warehouse is not filled:

 


2 replies

Badge +3

anyone with an idea?

Userlevel 5
Badge +9

Hi @Marc Johnson 

   With your existing data I can only explain theory and logic behind this calculation which I am sure you are well aware. If possible please give us simple test plan that exactly create your issue. Then we can have a close look.

regards,

Piyal