If we have a created Customer Order in a planned state.

 

After that the Inventory Parts get a new Cost, so total contribution margin amount will be incorrect.

 

Is there a way to run a job that recalucates ‘total contribution margin amount’ with the new Part Cost?

If I recreate the Customer Order it will work

2 replies

Forum|alt.badge.img+1
  • Author
  • Do Gooder (Customer)
  • Apr 22, 2024 8:30 PM UTC

if you update the Quantity on each line, it will take on the new part cost.


PRODQ
Superhero (Customer)
Forum|alt.badge.img+19
  • Superhero (Customer)
  • Apr 26, 2024 3:45 PM UTC

Is there a ‘highlight the line/right mouse button/recalculate price’ option (or off the RMB in the header)

 