Hi,

 

how can we easily reschedule a complete released DOP, without using APB?

 

We released the DOP, shop orders are created, however we want to push the complete structure forward. In APB you can drap and drop the DOP as a whole, but what is the easiest way to this without APB?

So all shop orders created within the DOP should move one weak further for example, preferably using drag and drop in the manufacturing visualiser for example

2 replies

Forum|alt.badge.img+11
  • Author
  • Sidekick (Partner)
  • 128 replies
  • December 15, 2022

I believe only APB can do this?


matt.watters
Ultimate Hero (Partner)
Forum|alt.badge.img+26
  • Ultimate Hero (Partner)
  • 699 replies
  • December 15, 2022

Been a while since using DOP. You should be able to modify the date of the top DOP Order and propagate the change upstream. Would need to have the settings of the Update Flags on each DOP Order in the structure for DOP Pegged SO/PO Update set properly to update their dates.