Perform Site MRP -1 day lead time flag in APPS9 vs APPS10

  • 17 March 2022
  • 2 replies
  • 85 views

Userlevel 2
Badge +5

Hi All,

In APPS9 ,on Perform Site MRP’  there is an option to Add 1 day leadtime  which does not appear in APPS10. Does anyone know if this has been removed or if there is a way to get this option in APPS10? Is there an alternative? The one alternative I am looking at is using the Picking time in the Site set up leve ( see screen shot below)

APPS 9

 

APPS10

 

 

Alternative to use Picking time on Site set up?

Thanks ,

Susan


This topic has been closed for comments

2 replies

Userlevel 7
Badge +23

In apps 10 you can instead define a Safety Lead Time in Inventory Part/Planning Data for any number of days. This results in that MRP plans a supply to arrive X number of days before it is needed on a demand. 

Userlevel 2
Badge +5

Thank you for this information.