Hi,
I have just received the working calendar for the rest of the year from some of our Suppliers.
These suppliers provide us with some external manufacturing operations. These operations have fixed lead times in the system for each kind of operation (created through Standard Operations menu).
My question is: Is there a way to create some sort of supplier calendar and add the working day exceptions for each supplier separately? This way we get a better idea on when we would get the parts delivered.
If so, how? If not, dos anyone has an workaround to this?
Many thanks in advance for all the support!