We face the following situation:
- MS level 1 defined some time ago having a forecasted qty of 500pcs for 02/10/2023
- setting this date (02/10/2023) as exception = non-working day are re-generating the calendars
- MS is automatically adding a new line with same qty on the next available working day 03/10/2023
- as consequence shop order requisitions are proposed for both demands (1shop order req on the 29/09/2023 for the demand of the 02/10/2023 + 1 shop order req for the 03/10/2023 for the newly added demand on the 03/10/2023); of course materials are planned too for the 2 requisitions
Did any of you experience this? is it related to a setting that I am missing?
We use IFS APPS9.
Thank you in advance for your support,
Mihaela
Here are some screen shots:
Initial state:
adding date as holiday:
impact in MS level1:
and proposed shop order requisitions: