Hi All,
Playing around with “Request Management” & “Work Task - Service”, I noticed something strange.
I created a Work Task - Service with Material. The material demand shows up on the IPAP - so far so good, but when I run MRP, it does not generate a Shop Order Requisition. Although I would expect this since there is not enough material on stock of my manufactured part.
I’ve added my steps below. Anybody have any suggestions?
Best Regards
Roel
Process:
Result: Nothing is happening on the IPAP. The MRP runs - demand is there but no Shop Order Requisition.