Hi Folks
We are using APPS 10 and looking at the various Lot Size options within IFS, when planning MRP requirements does the system start with the Min Lot size them move to Max then multiple or does one of these options take priority over the rest? (does one supersede the other)
Should the Max and Multiple be the same value?
Trying to figure out of there is some logic flow to these values if all three are filled in.
Min Lot Size: The value in this field indicates that the lot size for this part will be at least equal to the quantity specified. If the value is 0 (zero), the lot size will not be calculated.
Max Lot Size: The maximum lot size defines the maximum size of lots generated by material requirements planning (MRP).
Multiple Lot Size: A value in this field indicates that MRP will round up net requirements to a multiple of this value when calculating the receipts. Shop orders created from shop order requisitions will use multiple lot size values defined here.