Currently in the implementation process and were interested in using Kanban Circuits to replenish our production lines in two of our sites. After initial testing, it seems Kanban is not possible to be a separate module outside of our normal MRP replenishment (Planning method A with safety stock and standard lot size).
Our hope was Site A would produce and purchase parts via MRP to store in the warehouse. Site A, via distribution order generated through MRP, would send said material to Site B to store in their warehouse.
Both sites A and B have production lines to consume these parts. Current process, these parts are back flushed out of a generic “market” location which we are trying to get rid of. Kanban circuits seemed like an ideal way to restock these production lines.
If it is the case that we cannot use Kanban and also generate reqs with MRP, is there another way to accommodate the resupply of the assembly lines?