Hello.
We have an issue on our DOP structure’s due dates.
In our example, a DOP header has a Start date at 27/05/2022 and, when the structure has the statut “created”, every lines of it has a Due date at the same date of 27/05/2022.
After that, we release the DOP structure .
In standard, the DOP order due dates of WINCH-T40 and B-MODULE-BOIS are 27/05/22.
However, in the shop order the required dates of these components are 02/06/22 because they are called on the second operation of the shop order
This impacts the dates of shop orders and purchase orders of components managed in DOP (or MRP/DOP)
This does not impact the dates of shop orders and purchase orders of components managed in MRP because the MRP component need is triggered by the shop order (however if the MRP component is below a SF component managed in DOP, as the SF date is wrong the component date is wrong).
Have you allready encounter this issue ? and have you a way to avoid it ?