Hello team
For customer order line supply code with “purch order trans”, it has PO line link as Supply Chain Customer order analysis” screen being shown (Planned ship date =8/17/2023 same as PO planned receipt date) at beginning.
- Advance PO receipt date to 8/7/2023 and click Yes to “replicate change to pegged order”, but go to supply chain customer order analysis, the CO line’s planned ship date does not change to 8/7/2023 (or 8/10/2023 consider routing ID) and still keep as 8/17/2023 (not advance as it is).
-
Postpone PO receipt date to 9/4/2023 and click Yes to “replicate change to pegged order”, then go to supply chain customer order to analysis, the CO line’s planned ship date does change to 9/7/2023 (consider Routing ID).
-
Can you please help to check why CO planned ship date does not change when advance PO receipt date, but postpone does work? Any basic data need to set up or other action need to take?
Any questions please let me know.
Thanks
Susan