Hi All,

 

Below is the error I am getting in Background Job.

Any idea?

 

“Error when calculating the requirement date for Site/material SFR01/129650026, Class ABC C. The requirement date does not exist in the production line calendar.”

icon

Best answer by Pilar Franco 11 May 2023, 11:25

View original

1 reply

Userlevel 5
Badge +13

Hi,

This error means that your current manufacturing calendar associated in site SFR01 is not covering the date calculated by the background process.

You will need to expand the date range (extend the End date) and regenerate the corresponding calendar.

Also, if you are using production lines, check the calendar date range of the calendar associated to the production line.

Regards,

Pilar