Hello, 

I have a different picking lead time for each product family. Except that I can't enter this information on IFS, I can either enter it on the site in the "Inventory" tab or in the supply chain matrix which is based on the delivery information but does not take into account the product family. Do you know by any chance a method to enter a picking lead time for each product family? 


Thank you.
Lina


1 reply

Badge

Hi,

In the standard solution it is not possible to configure a picking lead time by product family. Maybe you can try a configuration with a custom field and a custom event. Create a custom field in the Product Family basic data where you specify the picking lead time and an event to retrieve/update the picking lead time in the order line.