Hi,

Using MWO with IFS Cloud 22R1, I noticed that the “Actual Worked Hours” are calculated using “Assignment Finish” date and time.

Is it the expected behavior ?

It make more sense to me that it would be calculated with “Work Finish” date and time.

Kind regards,

Lénaïc

Hi Lénaïc,

You are correct in your observation, this is not correct behavior.

This has been corrected in 22R1 SU6 by correction https://ifsdev.atlassian.net/browse/AMZWOP-7119