Hi Experts,

One of our customers would like to know if there’s a plan to include a task_unit tab in the baseline Task screen.

Even though the customer themselves could configure it, they want to know if the feature is going to be added in a later release.

 

Thanks,

Minindu

icon

Best answer by Isuranga Ediriweera 5 July 2021, 08:32

View original

This topic has been closed for comments

1 reply

Userlevel 4
Badge +7

Hi Minidu,

The relationship between the task table and the Task_unit table is already defined from the FSM baseline metadata.
If you want to use the task_unit table in the task screen as a tab, then you need to define the "Child relationships first".

Go to task screen from the UI designer. Then add the relationship information from the "Edit Child Relationships" as following.


After that the task_unit table will be available in the “Add screen fields” so you can use these task_unit fields as per the customer requirement.


From the UI designer the task_unit relationship has not been defines in the baseline task screen . Which means the task_unit and task tables relationships are not using in the current FSM design.

But we can create a relationship as above from the UI designer and use this table for customer requirement.

 

Kind Regards,