Using mworkorder apps10 UPD8,

I could see if send a work task to mobile “pool” with plan and final date, the date filter (tady, future etc) in mobile pool screen does not work.

The filter consider just the allocated date, not plan date of the work task.

 

The allocated date should work just for my service screen.

 

The problem is that in pool situation, there is no alocation date.

 

Is there a solution for this situation?

 

Tks

Hi everyone, Rnd recognized as a BUG and released a fix in UPD10.

Tk you all


Hi everyone,

Using mworkorder apps10 UPD8,

I could see if send a work task to mobile “pool” with plan and final date, the date filter (tady, future etc) in mobile pool screen does not work.

The filter consider just the allocated date, not plan date of the work task.

 

The allocated date should work just for my service screen.

 

The problem is that in pool situation, there is no alocation date.

 

Is there a solution for this situation?

 

Tks

Fixed and included in:
Version: Mobile Work Order - App10 UPD10 HF2 (10.10.0.2)

mWO Android:  4 . 1 0 . 0 . 4 
mWO Windows: 4.10.0.4 
mWO iOS: 4.30.1 
mWO Cloud:   4.10.0.2 

TAS Version :   10.9.299.0 
FNDMOB :   10.11.11.0 