Hi All

In MWO we use surveys for questions before Work Started, or before Completing a work task.  These surveys include mandatory steps that should be completed before the Work Task is reported.  If the user is not able to provide a proper answer then they should not be allowed to report in the task.  These tasks are set as Terminating Questions in the survey, but when a user answers these, they are still taken to the Report in page.

Is it possible to set it up so that if a user enters Terminating answer they are taken back to the Work Details rather than being allowed to continue to report in?

Hi

You can achieve this via the workflow configuration type “Configured Work Task”. You can direct the user into different stages of the workflow when a survey question is terminated.