We have a situation with our Maintenance Plan where, if a preventive maintenance is anticipated, the Planned Value colunm does not update. Do you have any tips on how where can we set this colunm to be flexible?

A little background on the situation described: Below you can see the maintenance plan for one of our trucks. The actions are based on how many hours the machine has worked. We anticipated a 500h revision 90h before it was due. When the WO was closed, we would like that the Planned Value would change from 9113h, to 9023h (since 90h were anticipated). But the values remain still.

 

Thank you

Hi, I cannot tell which version of IFS you are running so hopefully this is still applicable. For PM’s that you wish to be dynamic in the way you have described you need to use the ‘Performed Value Based’ setting. 