If a user has a mWO task and starts it, there will be normally a completion on the same day or even the next day/week/month. When the user forgets to ‘pauze’ the task, it will lead to a lot of hours worked on the task.

Massive number of hours booked

In the example above I've completed a mWO task that was entered/started quite some time. In green I see at (1) that for Wednesday November 10th there are approx 1990 hours booked.

Question: is it possible to spread the hours automatically (backwards in time) over the scheduled hours?

Version 10.13..1360.0 is showing in mWO (Windows)

Hi @eqbstal , It is not possible to spread the hours automatically (backwards in time) in core solution.

There a workflow setting to set Auto time off and user can manually enter time report. Not sure that helps.

Thanks.


Bandula,

Thanks for your answer. Sure this is not what I hoped for, but some things are just as they are.