Hi,
We’ve been using IFS for a year or so but repetitively see an issue with negative ETC costs generated on resource forecasts that then feed into project financial forecasts, and cause cascading issues.
Working example below:
I have done a little digging but still confused as we were never educated on some of the underlying calculations that occur. In the example:
- PM has defined 0 ETC hours to complete on this activity.
- ETC cost is pulling through a large negative cost.
- Drilling down it appears to be an issue with Cost Elements whereby negative User Hours are posted into ETC leading to the negative ETC cost.
- Why do ETC hours in cost elements display differently to the main resource forecast screen?
Unsure what “cost elements” are within IFS and ultimately how they are controlled and who typically within an organisation controls them. Can anyone please help shed light on this?
Thanks
Ian