from relase 22R2 RESOURCE Crews were introduced for projects update. However is not very clear how to use them.
I have createda resource group-crew type, and it is available ,to use in service, manufacture , maintenance and projects
then created a crew with periods and members
however when I want to use this crew in a project or WO/ routing I don’t have the option
Project’s doesn’t seem to allow any resource different to person type
WO only tools/ Equipment and person
any idea how to allocate resource group type crew