Hello Good Folks in the Community,
I’ve encountered an issue where “Project Transactions” created off of direct inventory issues to a Project Activity, doesn’t fetch the “Sales Price” from a “Specific Sales Prices” defined against the same Project.
Environment - Apps 10
Version - UPD 12
See the following scenario:
The Project in question has a “Specific Sales Price” (with a mark up defined against a “Material” type Report code (as highlighted in screenshot below) in “Project Setup Parameters” > “Pricing” tab.
However, after Issuing some “Parts” against a Project Activity and execute the “Create Project Transaction” command in “Project Materials and Services” page resulting dialog box shows me that my “Internal Price” (Part Cost x Qty) is as same as the “Sales Price” (despite having a Specific Sales Price defined in the Project).
Consequently the resulting “Project Transaction” has the “Internal Price” as the “Sales Price”, but i am expecting the Sales Price to be “Internal Price” x Markup % (see below).
Most importantly this Project in question is a T&M (Time and Material) one, hence i need the Sales Price at the Project Transaction to bill it against the customer via the “Create Project Invoice” wizard.
When we technically investigated the same scenario, it was revealed that there is a code that has been deployed via an IFS bug fix which is stopping the Sales Price being fetched when the associated “Report Code” is of type “Material”.
I am confused as to why such a block has been introduced(or if we have not understood the code correctly - as i am not a technical person) by IFS.
Or I might be wrong here and/or missing a setup or a step using which i can get the system to fetch a “Sales Price” to a “Project Transaction” coming off of direct material issues to a Project.
Any direction/guidance on this issue is much appreciated, since at the moment I am clueless and have exhausted all avenues to check.
Thanks a bunch for the support!