Multiple project time reporting transactions available on different account dates for the same employee , same project activity and same report code. Transactions are Approved > transferred to cost accounting and GL is updated. Project actual cost is available.
In Activity> project connections , the sum up amount from above transactions are available.
However, Project connection> RMB> Project transactions routes to the project transaction screen, but all the corresponding transactions are not correctly filtered & fetched.
How do we resolve this?