Question

Project MS vs. PMRP

  • 19 January 2022
  • 1 reply
  • 137 views

Badge +2

Hi.

 

Please, I have issue with project planning…

I want use MS (Master Scheduling) where I want put some ,,forecast” to manufactured part, and this MS part is connected to project activity.

In Master scheduling header I try to use Create S/P Req → Create S/P from MRP option, but when I Run MS calculation and then PMRP, PMRP dont create any proposals.

  • I know, that MS option Create S/P Req generate proposals from MS, but I need PMRP as prosals source and MS only as qty forecast purpose

My goal is, that I want use combination of MS part and PMRP to create Shop Order Proposal from PMRP.

Is that even possible ???

Thanks for any hint.


1 reply

Userlevel 5
Badge +10

Check if your “Project PNG” entered in your MS part. 

Reply