Dear all,

I linked a customer order line with supply code Shop Order to a projct activity. 

I expected the planned costs to be the costs from cost set 1 of the concerned part (as correctly shown in cost column in order line) and as described in IFS-documentation:

 

 

BUT:

In project activity the planned costs are the level costs of the part, not the accum. cost:

 

 

I made various tests with differing parts on different environments where the planned costs in activity have shown these outcomes:

  • cost set 2 of the part
  • Accumulated Cost – Level Cost
  • Level Cost (as stated above and shown in screenshot)

 

 

What should be the correct behaviour?

Why do I observe so many differing situations? Which setup is interfering here?

 

 

 

Thanks a lot!

Mattis

@Bob Corrigan 

@Pradeep de Alwis 

@anmise 

Hi @IFSmattis 

Please check the ‘Product Structure’ of the manufactured part and see how many ‘Phantom Parts’ are there in the structure?

 


@IFSmattis  I am running into the same issue, any thoughts as to how you may have resolved this.