IFS Cloud 22R2 - Activity Resource’s Planned Cost seems incorrect when there is some reported time

  • February 2, 2023
  • 2 replies
  • 121 views

Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+16

Hi Community,

 

The below issue comes in IFS Cloud 22R2 version.

 

Internal Price for the Project has been set

 

Now, 1 hour has been reported to Activity A1. With the cost of 150

This is correct as it has properly fetched from the Internal Price setup.

 

Create a Resource with a cost of 20

 

There are no Persons connected to this Resource

 

Add this Resource to a different Activity A2 in the same Project

Why the Planned Cost is shown as “150” here ?

 

This problem comes when there is already reported time for some activity in the project.

Anybody has an idea ?

Best answer by wrprabash

Hi Community,

 

The below issue comes in IFS Cloud 22R2 version.

 

Internal Price for the Project has been set

 

Now, 1 hour has been reported to Activity A1. With the cost of 150

This is correct as it has properly fetched from the Internal Price setup.

 

Create a Resource with a cost of 20

 

There are no Persons connected to this Resource

 

Add this Resource to a different Activity A2 in the same Project

Why the Planned Cost is shown as “150” here ?

 

This problem comes when there is already reported time for some activity in the project.

Anybody has an idea ?

Hi Tharindu,

When you setup a specific price (150) for a project as you have done, then it overrides any other internal price setups for that project. I think this is how the project internal price logic is designed. That is why you always get 150 for the reporting done on this project.

Regards,

Roshan

 

2 replies

wrprabash
Hero (Partner)
Forum|alt.badge.img+10
  • Hero (Partner)
  • 82 replies
  • Answer
  • February 2, 2023

Hi Community,

 

The below issue comes in IFS Cloud 22R2 version.

 

Internal Price for the Project has been set

 

Now, 1 hour has been reported to Activity A1. With the cost of 150

This is correct as it has properly fetched from the Internal Price setup.

 

Create a Resource with a cost of 20

 

There are no Persons connected to this Resource

 

Add this Resource to a different Activity A2 in the same Project

Why the Planned Cost is shown as “150” here ?

 

This problem comes when there is already reported time for some activity in the project.

Anybody has an idea ?

Hi Tharindu,

When you setup a specific price (150) for a project as you have done, then it overrides any other internal price setups for that project. I think this is how the project internal price logic is designed. That is why you always get 150 for the reporting done on this project.

Regards,

Roshan

 


Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+16

Hi @wrprabash ,

 

Thank you for pointing that.

Yes, it seems like that is the behaviour.