Hi people, can anybody tell me what are the general differences between MRP vs P-MRP qith respect to material demand by an Project activity. Thx in advance...
MRP and PMRP are both very similar. They user data from Masters, Supply, Demand and Product Structures (BOMS) to calculate a purchasing and Production Plan for Project and Standard Inventory.
Some key differences are:
>PMRP does not create Supplier Schedules or Production Schedules and does not see any demand that is not Project Connected.
>A Planned Netting Group (PNG) is used by PMRP to move supply to where it is most needed by creating Material Transfer Requisitions
>PMRP does not plan to use Alternate Components where MRP may.
Without remembering much details, I think P-MRP (Project MRP) considers only demands and supply that are connected to project activities (that has project id and activity sequence). Otherwise most of the functionality is the same, I think.
Hi folks,