We have a customer which uses Project Management with Invoice Plan.

The Plan Revenue is calculate but it was necessary to setup Posting Rule PRJI2.

Is this the standard behaviour?

Vasco Silva

Hi Vasco Silva,

Yes, this is standard behaviour. Otherwise IFS does not know which Cost-/Revenue Element should be used. IFS checks the posting control (in your case PRJI2) to find out the correct Revenue element.

That is the same behavior for planned costs through demands, ressources etc. (Then posting controls for M1, M40, etc. must be defined.)

Best Regards
Patrick


Hi Vasco Silva,

Yes, this is standard behaviour. Otherwise IFS does not know which Cost-/Revenue Element should be used. IFS checks the posting control (in your case PRJI2) to find out the correct Revenue element.

That is the same behavior for planned costs through demands, ressources etc. (Then posting controls for M1, M40, etc. must be defined.)

Best Regards
Patrick

Thanks for the information.


Reply