Question

MRP 'Original Due' and 'Planned Due'

  • 26 June 2020
  • 1 reply
  • 150 views

Userlevel 3
Badge +7

Hi guys,

In ‘Shop Order Requisitions’, there are two columns called ‘Original Due’ and ‘Planned Due’. This determine the ‘Need Dates’ for the works orders that are raised by accepting the requisitions in question. In turn, dictating to APB (our CBS engine) what to prioritize when a trade-off is required given resource limitations.

 

How can those dates be changed? Namely, for SST items under planning method B/C.  For demand released by a customer or projects that would involve editing the required date, performing MRP and alignment via MRP Action Proposals.

 

How can we change the Orig. and PLD Due dates for SST items so they are called for now. 

 

thanks,

jay

 


1 reply

Badge +1

In shop Order Requisitions , original due date is the due date when it creates first time. Planned due date also set to same date. But user can edit planned due date later.

Items with planning methods B and C, do  not plan by MRP.

For MRP planned items, once MRP is run, it will generate SOR’s with demand due date as original and planned due date. if the required date is changed, then after running MRP, it will delete old SOR and create a new SOR with new dates. Still user can manually change only planned due date in SOR’s.

Reply