Hi @CDCZdeneB ,
The UOM other than hours are used for the work center with work center code Resource Requirement Planning (RRP) and not for the regular work center which are used in manufacturing routings.
RRP is a very high level capacity planning sort of rough cut capacity planning where you can roughly estimates whether you have enough capacity to meet the production plans which are deduced based on Master Scheduling & Sales & operational Planning.
RRP means long-term planning without respect to details and the goal of RRP is to balance resources that take a long time to change against existing demand (bottle necks)
For RRP, work centers are created such as storage space, personnel, transport capacity, supplier capacity etc. where you can use different UOM accordingly. RRP routings are created separately.
Hope this helps!!
Regards,
Mithun K V
Hi @CDCZdeneB ,
The UOM other than hours are used for the work center with work center code Resource Requirement Planning (RRP) and not for the regular work center which are used in manufacturing routings.
RRP is a very high level capacity planning sort of rough cut capacity planning where you can roughly estimates whether you have enough capacity to meet the production plans which are deduced based on Master Scheduling & Sales & operational Planning.
RRP means long-term planning without respect to details and the goal of RRP is to balance resources that take a long time to change against existing demand (bottle necks)
For RRP, work centers are created such as storage space, personnel, transport capacity, supplier capacity etc. where you can use different UOM accordingly. RRP routings are created separately.
Hope this helps!!
Regards,
Mithun K V
Thanks for very quick answer, clear, I will leave the topic as open for a short time, if nobody will react, I will mark your answer as the best one and close the ticket.
Regards,
Zdenek