Hi all,
We are implementing Aurena and doing some testing and I have a shop order where the start date and finish dates are the same. The routing is set up with no M/C run time and a Labour run time of 240 hours.
The need date is 3 months in the future.
Reardless of the direction of scheduling should the operation hours be reflected in the Start date and finsh date, i.e. 240 hours different. Thereofre with a need date of 21/10/24 and backward scheduling have a finish date of 18/10/24 and a Start date of 06/09/24
Thanks in advance