Schedule operations based on a fixed date

  • 20 April 2022
  • 2 replies
  • 137 views

Userlevel 6
Badge +14

Hi all,

Sometime we have to start an operation on a fixed date. The other operations then have to be rescheduled according to that date. In the example below.

Operation 20 must start 27-05-2022 06:00:00.

The following operations are then rescheduled, but the operation (10) before does not rescheduled . How do we make it do that?

 

icon

Best answer by Björn Hultgren 20 April 2022, 18:42

View original

2 replies

Userlevel 7
Badge +23

If you use the rescheduling options available from Manufacturing Visualizer (Enterprise Explorer) or Visual Planning (Aurena), you have the option Compress Operations. If you reschedule operation 20 to start 06:00 on the 27th and select this option, operation 10 would have been backward scheduled to finish 06:00 on the 27th (or whenever the previous work time is).

 

Userlevel 6
Badge +14

Thanks @Björn Hultgren ,

It was the functionality I was looking for.