Skip to main content

Hi

using IFS apps 10 and have been playing around with the Resource structures and resource analysis to replicate actual resource constraints.

however there is an icon on the resource structure that I do not know the meaning to (below highlighted in red) can anyone help?

 

Also can anyone explain the difference 1) Schedule capacity, 2) Adjusted capacity and 3) utilization capacity on the resource analysis graph?

 

kind regards

Jamie 

The Triangle indicates, as I can remember, that you have overplanned the resource at some point in time. (meaning the planned values exceed the available capacity)