Hello,
Our business works on a project basis. We want to be able to reserve parts and track them, from procurement to production, on a project basis. So we are evaluating the possibility of working with PMRP.
Where it gets complicated is that we need to purchase for some article larger volume to take advantage of economies of scale. With the possibility of taking into account the surplus stock in the calculation of the PMRP, our need is met.
However, we are encountering a blocking problem at the purchasing level. It seems that the PMRP does not take into account the ongoing purchase orders for inventory replenishment (therefore not related to the project). The PMRP does not consider them and asks us to buy the parts, while a purchase is in progress at the general stock level.
Have you encountered the problem and is there a solution?
Thanks in advance for your expertise!
Regards,
Coralie