Hi All
Hopefully an easy one.
Scenario, Part A( manufactured) is made from Part B (purchased), currently both set up as finite with a lead time.
At the Begining Part A is scheduled for 100 days from now based on lead time, so far so good.
A PO is created for part B and the planned arrival date can now be earlier or later than expected ,
Now when i run APB i need this new arrival date (Actual supply) to supersede the default lead time.
What settings / process do i need to incorporate in order for this to happen?
Regards
Ian